Lagoo Builders And Consultants Pvt Ltd

Deedo IDDD-ZQD3

Of 4 registrations whose promised date has arrived, 2 kept it (50%). The rest ran a median 29 mo late.

Projects55 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay29 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 5 ran past the RERA date

Months late against the original RERA promise, per registration

5 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
PrernaP53100000286Sangli Miraj Kupwad (M Corp.)Certificate Signed1 Jun 20191 Jun 2019On date
AkankshaP53100021422Sangli Miraj Kupwad (M Corp.)Certificate Signed30 Sep 202230 Sep 2022On date
VastushreeP53100026711Sangli Miraj Kupwad (M Corp.)Certificate Signed30 Mar 202430 Mar 2024+31 mo*
ChitrarekhaP53100030599Sangli Miraj Kupwad (M Corp.)Certificate Signed31 Aug 202431 Aug 2024+26 mo*
Yashshree VastuP53100055628MirajCertificate Signed31 Mar 202731 Mar 2027On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology