Of 4 registrations whose promised date has arrived, 3 kept it (75%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.

Projects48 RERA registrations
Kept RERA date75%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time84registered sale deeds
Regulatory cases0none on record

3 registrations of 8 ran past the RERA date

Months late against the original RERA promise, per registration

8 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Hillview ResidencyP52100001962Pune (M Corp.)Certificate Signed24 May 201924 May 2019On date
Hill View Residency Phase I Project II Building A And BP52100014848HaveliCertificate Signed30 Dec 202230 Dec 2022On date
Hillvew Residency Phase I Project III Bldg N And OP52100014885Pune CityCertificate Signed30 Dec 202330 Dec 2023On date
Hillview Residency P CommercialP52100052705KothrudCertificate Signed30 Sep 202430 Sep 2025+12 mo
Hillview ResidencyP52100053658Pune (M Corp.)Certificate Signed31 Dec 202631 Dec 2026On date
Hillview ResidencyP52100078157Pune (M Corp.)Certificate Signed31 Dec 202631 Dec 2026On date
Hillview ResidencyP52100079167Pune (M Corp.)Certificate Signed30 Jun 202730 Oct 2027+4 mo
Hillview ResidencyP52100079466Pune (M Corp.)Certificate Signed30 Jun 202730 Oct 2027+4 mo