KoltePatil Integrated Townships Limited

Of 9 registrations whose promised date has arrived, 5 kept it (56%). The rest ran a median 22 mo late.

Projects810 RERA registrations
Kept RERA date56%Maharashtra: 73%
Median delay22 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases1no insolvency

4 registrations of 10 ran past the RERA date

Months late against the original RERA promise, per registration

10 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Life Republic Sector R16 - 16th AvenueP52100009640JambeCertificate Signed30 Dec 202230 Dec 2022On date
Life Republic Sector R3 3rd AvenueP52100016987JambeCertificate Signed30 Dec 202230 Dec 2022On date
Life Republic Sector R9-Oro AvenueP52100017116JambeCertificate Signed31 Jul 202431 Jul 2024On date
Life Republic Sector R16 16th Avenue ArezoP52100018539JambeCertificate Signed30 Dec 202330 Dec 2023On date
Life Republic Sector R7- 7th Avenue- i TowersP52100022154MulshiCertificate Signed30 Dec 202430 Dec 2024+22 mo*
Life Republic - Sector R 17 B - 17 B Avenue - NoraP52100022278JambeCertificate Signed30 Mar 202230 Mar 2022On date
Life Republic Sector R16 16th Avenue ArezoP52100023317JambeCertificate Signed30 Dec 202431 Dec 2024+22 mo*
Life Republic Sector C1 - City ElanzaP52100026426JambeCertificate Signed31 Jul 202331 Jul 2023+39 mo*
Life Republic Sector R16 16th Avenue ArezoP52100031799JambeCertificate Signed31 Oct 202531 Oct 2025+12 mo*
Life Republic Sector R13/13th Avenue/Aros/Phase-IIP52100054550NereCertificate Signed30 Jun 202830 Jun 2028On date