Keystone Properties
Of 2 registrations whose promised date has arrived, 1 were never extended past it (50%). When extended, the date moved a median 18 mo — longer than Maharashtra's 4 mo.
Projects12 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay18 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
1 registration of 2 moved past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| My Home PunawaleP52100004634 | Punawale | Certificate Signed | 30 Jun 2021 | 30 Dec 2022 | +18 mo |
| My Home PunawaleP52100033551 | Punawale | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology