Company or firm · first RERA registration 2024
Keystone Communities Llp
None of 5 registrations has reached its promised completion date yet.
Projects55 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
5 registrations of 5 ran past the RERA date
Months late against the original RERA promise, per registration
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Keystone Elevate-Tower A1P50400077624 | Wardha | Certificate Signed | 31 Dec 2032 | 30 Apr 2033 | +4 mo |
| Keystone Elevate-Tower B1P50400079284 | Wardha | Certificate Signed | 31 Dec 2032 | 30 Apr 2033 | +4 mo |
| Keystone Elevate-CommercialP50400079468 | Nalwadi | Certificate Signed | 31 Dec 2032 | 30 Apr 2033 | +4 mo |
| Keystone Elevate-Tower A2P50400079611 | Nalwadi | Certificate Signed | 31 Dec 2032 | 30 Apr 2033 | +4 mo |
| Keystone Elevate-Tower C1PR1340002600042 | Nalwadi | Certificate Signed | 31 Dec 2032 | 30 Apr 2033 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology