Company or firm · first RERA registration 2017
Keyana Estate Llp
Of 5 registrations whose promised date has arrived, 3 were never extended past it (60%). When extended, the date moved a median 15 mo — longer than Maharashtra's 4 mo.
Projects15 RERA registrations
Kept RERA date60%Maharashtra: 73%
Median delay15 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases1no insolvency
2 registrations of 5 moved past the RERA date
Months late against the original RERA promise, per registration
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Regulatory order | Kalpataru RadianceRegulatory order: PROJECT NAME:Kalpataru Radiance B (Regulatory Case No. 174 of 2024) dated 13 March 2024. | 13 Mar 2024 |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Kalpataru RadianceP51800000482 | Borivali | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| Kalpataru RadianceP51800000579 | Borivali | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| Kalpataru RadianceP51800000591 | Borivali | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| Kalpataru RadianceP51800000810 | Borivali | Certificate Signed | 30 Dec 2023 | 30 Dec 2024 | +12 mo |
| Kalpataru RadianceP51800013245 | Borivali | Certificate Signed | 30 Jun 2022 | 30 Dec 2023 | +18 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology