Of 4 registrations whose promised date has arrived, 4 were never extended past it (100%).
Projects34 RERA registrations
Kept RERA date100%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record
No registration has been extended past its RERA date
Months late against the original RERA promise, per registration
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Kiran ShubhamkarotiP52100010215 | Sus | Certificate Signed | 30 Dec 2018 | 30 Dec 2018 | On date |
| Kiran ShubhamkarotiP52100010995 | Sus | Certificate Signed | 30 Jul 2018 | 30 Jul 2018 | On date |
| Kiran SanklpP52100011477 | Sus | Certificate Signed | 31 Dec 2017 | 31 Dec 2017 | On date |
| Kiran SuyogP52100014252 | Pune (M Corp.) | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology