Of 4 registrations whose promised date has arrived, 4 were never extended past it (100%).

Projects34 RERA registrations
Kept RERA date100%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record
Kashinath Ganesh Nehete developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

No registration has been extended past its RERA date

Months late against the original RERA promise, per registration

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Kiran ShubhamkarotiP52100010215SusCertificate Signed30 Dec 201830 Dec 2018On date
Kiran ShubhamkarotiP52100010995SusCertificate Signed30 Jul 201830 Jul 2018On date
Kiran SanklpP52100011477SusCertificate Signed31 Dec 201731 Dec 2017On date
Kiran SuyogP52100014252Pune (M Corp.)Certificate Signed31 Dec 201831 Dec 2018On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology