Company or firm · first RERA registration 2017
Karrm Infrastructure Private Limited
Of 5 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 89 mo late.
Projects35 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay89 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases35includes insolvency
5 registrations of 5 ran past the RERA date
Months late against the original RERA promise, per registration
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
Show all 35 casesShow fewer
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Karrm Residency -4P51700003215 | Kasagaon | Certificate Signed | 31 May 2019 | 30 Nov 2020 | +89 mo* |
| Karrm PanchtatvaP51700007680 | Kasagaon | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | +34 mo* |
| Karrm Gardens - 1P51700008284 | Ambarnath(M Cl) | Lapsed | 31 May 2019 | 30 Nov 2020 | +89 mo* |
| Karrm PanchtatvaP51700009304 | Kasagaon | Certificate Signed | 31 Dec 2018 | 30 Oct 2020 | +94 mo* |
| Karrm PanchtatvaP51700010325 | Kasagaon | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | +46 mo* |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology