Skip to content
Company or firm · first RERA registration 2017

Kapleshwara Builders And Developers

Of 1 registration whose promised date has arrived, 1 kept it (100%).

Projects11 RERA registration
Kept RERA date100%Maharashtra: 73%
Median delay0 monone ran late
Flats sold, all time0registered sale deeds
Regulatory cases1no insolvency

No registration has run past its RERA date

Months late against the original RERA promise, per registration

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

CaseProjectDate
complaintPinnacle GloriaComplaint CC12600302Not on record

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Pinnacle GloriaP51700008627Thane (M Corp.)Completed1 Oct 2022—On date