Company or firm · first RERA registration 2017
Kanakia Spaces Realty Private Limited
Deedo IDDD-AZ45Of 8 registrations whose promised date has arrived, 6 kept it (75%). The rest ran a median 15 mo late — longer than Maharashtra's 4 mo.
Projects88 RERA registrations
Kept RERA date75%Maharashtra: 73%
Median delay15 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
2 registrations of 8 ran past the RERA date
Months late against the original RERA promise, per registration
8 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Kanakia Wallstreet Wing AP51800000121 | Andheri | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
| Kanakia ParisP51800000122 | Andheri | Certificate Signed | 28 Jun 2021 | 28 Dec 2021 | +6 mo |
| Kanakia HollywoodP51800000123 | Andheri | Certificate Signed | 30 Sep 2019 | 30 Sep 2019 | On date |
| Kanakia LevelsP51800000223 | Formborivali | Certificate Signed | 31 Oct 2019 | 30 Oct 2021 | +24 mo |
| Kanakia RainforestP51800000224 | Andheri | Certificate Signed | 30 Mar 2021 | 30 Mar 2021 | On date |
| Kanakia MiamiP51900000206 | Ward Gnorth | Certificate Signed | 30 Sep 2020 | 30 Sep 2020 | On date |
| Kanakia SevensP51800000388 | Andheri | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| Kanakia Zenworld Phase IP51800008343 | Kurla | Certificate Signed | 30 Mar 2023 | 30 Mar 2023 | On date |