Company or firm · first RERA registration 2017
Kamalraj Associates
Deedo IDDD-3KNVOf 4 registrations whose promised date has arrived, 1 kept it (25%). The rest ran a median 12 mo late.
Projects34 RERA registrations
Kept RERA date25%Maharashtra: 73%
Median delay12 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
3 registrations of 4 ran past the RERA date
Months late against the original RERA promise, per registration
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Kamalraj ParijatP52100002591 | Dighi | Certificate Signed | 30 Nov 2018 | 30 Nov 2019 | +12 mo |
| Kamalraj Haridwar C BuildingP52100010254 | Dighi | Certificate Signed | 31 Jul 2022 | 31 Jan 2023 | +6 mo |
| Kamalraj ParijatP52100019167 | Dighi | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| Kamalraj Parijat C Commercial MhadaP52100025042 | Dighi | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | +46 mo* |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology