Kamalraj Associates

Deedo IDDD-3KNV

Of 4 registrations whose promised date has arrived, 1 kept it (25%). The rest ran a median 12 mo late.

Projects34 RERA registrations
Kept RERA date25%Maharashtra: 73%
Median delay12 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

3 registrations of 4 ran past the RERA date

Months late against the original RERA promise, per registration

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Kamalraj ParijatP52100002591DighiCertificate Signed30 Nov 201830 Nov 2019+12 mo
Kamalraj Haridwar C BuildingP52100010254DighiCertificate Signed31 Jul 202231 Jan 2023+6 mo
Kamalraj ParijatP52100019167DighiCertificate Signed30 Dec 202130 Dec 2021On date
Kamalraj Parijat C Commercial MhadaP52100025042DighiCertificate Signed30 Dec 202230 Dec 2022+46 mo*
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology