Kalpataru Gardens Pvt. Ltd

Of 4 registrations whose promised date has arrived, 4 kept it (100%).

Projects44 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay0 monone ran late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

No registration has run past its RERA date

Months late against the original RERA promise, per registration

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Kalpataru CrestP51800000795KurlaCertificate Signed31 Dec 201931 Dec 2019On date
Kalpataru Serenity - Bldg. 5P52100001267Manjari BkCertificate Signed30 Dec 202230 Dec 2022On date
Kalpataru Serenity - Bldg. 2P52100015855Manjari BkCertificate Signed30 Oct 202430 Oct 2024On date
Kalpataru Serenity - Bldg. 3P52100034075Manjari BkCertificate Signed31 Dec 202531 Dec 2025On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology