Individual promoter · first RERA registration 2022
Kailas Suresh Satelkar
Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 11 mo late.
Projects33 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay11 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
2 registrations of 3 ran past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sai DarbarP52900033068 | Kankavli | Certificate Signed | 31 Oct 2023 | 31 Oct 2023 | On date |
| Sat BangalaP52900045584 | Humrath | Certificate Signed | 5 May 2025 | 5 May 2025 | +17 mo* |
| Samarth Sai ResidencyP52900078236 | Kankavali | Certificate Signed | 28 May 2028 | 28 Sep 2028 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology