Company or firm · first RERA registration 2017

Kaamdhenu Builders

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 13 mo late — longer than Maharashtra's 4 mo.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay13 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Kaamdhenu LuxuriaP52000000786BokadviraCertificate Signed30 Sep 202230 Jun 2023+9 mo
Kaamdhenu CelestiaP52000010844BokadviraCertificate Signed28 Aug 202331 Dec 2024+16 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology