Company or firm · first RERA registration 2021
K S Shreeya Infrastructure Pvt Ltd
Deedo IDDD-71PXOf 6 registrations whose promised date has arrived, 5 kept it (83%). The rest ran a median 27 mo late — longer than Maharashtra's 4 mo.
Projects66 RERA registrations
Kept RERA date83%Maharashtra: 73%
Median delay27 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
1 registration of 6 ran past the RERA date
Months late against the original RERA promise, per registration
6 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Mauli Nagar 09 Sector AP50500031387 | Jamtha | Certificate Signed | 28 Sep 2024 | 28 Sep 2024 | On date |
| Mauli Nagar 09 Sector DP50500031400 | Jamtha | Certificate Signed | 28 Sep 2024 | 28 Sep 2024 | On date |
| Mauli Nagar 09 Sector CP50500031522 | Jamtha | Certificate Signed | 29 Sep 2023 | 29 Sep 2023 | On date |
| Mauli Nagar 09 Sector FP50500032171 | Jamtha | Certificate Signed | 23 Sep 2023 | 31 Dec 2025 | +27 mo |
| Mauli Nagar 09 Sector BP50500032188 | Jamtha | Certificate Signed | 23 Sep 2023 | 23 Sep 2023 | On date |
| Mauli Nagar 09 Sector EP50500032353 | Jamtha | Certificate Signed | 23 Sep 2023 | 23 Sep 2023 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology