Company or firm · first RERA registration 2017

K K Construction

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 11 mo late — longer than Maharashtra's 4 mo.

Projects33 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay11 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 3 ran past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Padhye Complex Phase IIP99000001884PalgharCertificate Signed30 Dec 202230 Dec 2022On date
Crescentpoint-IIP99000020521PalgharCertificate Signed30 Jun 202331 Dec 2024+18 mo
K K Park - Phase IP99000024440PalgharCertificate Signed31 Dec 202730 Apr 2028+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology