Company or firm · first RERA registration 2017
K K Construction
Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 11 mo late — longer than Maharashtra's 4 mo.
Projects33 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay11 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
2 registrations of 3 ran past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Padhye Complex Phase IIP99000001884 | Palghar | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| Crescentpoint-IIP99000020521 | Palghar | Certificate Signed | 30 Jun 2023 | 31 Dec 2024 | +18 mo |
| K K Park - Phase IP99000024440 | Palghar | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology