Company or firm · first RERA registration 2017
Jsb Buildcon Llp
Of 2 registrations whose promised date has arrived, 0 were never extended past it (0%). When extended, the date moved a median 18 mo — longer than Maharashtra's 4 mo.
Projects12 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay18 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
2 registrations of 2 moved past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Nakshatra GreensP99000005051 | Vasaivirar City (M Corp) | Certificate Signed | 30 Jun 2018 | 30 Jun 2019 | +12 mo |
| Nakshatra GreensP99000008753 | Vasaivirar City (M Corp) | Certificate Signed | 31 Dec 2019 | 30 Dec 2021 | +24 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology