Of 2 registrations whose promised date has arrived, 0 were never extended past it (0%). When extended, the date moved a median 18 mo — longer than Maharashtra's 4 mo.

Projects12 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay18 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
Jsb Buildcon Llp developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

2 registrations of 2 moved past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Nakshatra GreensP99000005051Vasaivirar City (M Corp)Certificate Signed30 Jun 201830 Jun 2019+12 mo
Nakshatra GreensP99000008753Vasaivirar City (M Corp)Certificate Signed31 Dec 201930 Dec 2021+24 mo