Company or firm · first RERA registration 2022

Jairajhappyhomes

Of 4 registrations whose promised date has arrived, 3 kept it (75%). The rest ran a median 9 mo late — longer than Maharashtra's 4 mo.

Projects35 RERA registrations
Kept RERA date75%Maharashtra: 73%
Median delay9 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 5 ran past the RERA date

Months late against the original RERA promise, per registration

5 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
JADE AVENUE-Residential WingP51900033215Mumbai CityCertificate Signed30 Jul 202730 Jul 2027On date
Jade GardensP51800033601KurlaCertificate Signed31 Oct 202531 Oct 2025On date
Jade GardensP51800033945KurlaCertificate Signed31 Oct 202531 Oct 2025On date
Jade GardensP51800033954KurlaCertificate Signed31 Oct 202531 Oct 2025On date
Jade Avenue Commercial WingP51900050274Mumbai CityCertificate Signed30 Jun 202531 Mar 2026+9 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology