Company or firm · first RERA registration 2022
Jairajhappyhomes
Of 4 registrations whose promised date has arrived, 3 kept it (75%). The rest ran a median 9 mo late — longer than Maharashtra's 4 mo.
Projects35 RERA registrations
Kept RERA date75%Maharashtra: 73%
Median delay9 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
1 registration of 5 ran past the RERA date
Months late against the original RERA promise, per registration
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| JADE AVENUE-Residential WingP51900033215 | Mumbai City | Certificate Signed | 30 Jul 2027 | 30 Jul 2027 | On date |
| Jade GardensP51800033601 | Kurla | Certificate Signed | 31 Oct 2025 | 31 Oct 2025 | On date |
| Jade GardensP51800033945 | Kurla | Certificate Signed | 31 Oct 2025 | 31 Oct 2025 | On date |
| Jade GardensP51800033954 | Kurla | Certificate Signed | 31 Oct 2025 | 31 Oct 2025 | On date |
| Jade Avenue Commercial WingP51900050274 | Mumbai City | Certificate Signed | 30 Jun 2025 | 31 Mar 2026 | +9 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology