Hezal Infrastructure

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 7 mo late.

Projects33 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay7 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 3 ran past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Gold CoastP52000047964WahalCertificate Signed30 Jun 202630 Oct 2026+4 mo
Hari OmP52000048235WahalCertificate Signed31 Dec 202531 Dec 2025+10 mo*
Jai Ganesh SapphireP52000048565WahalCertificate Signed31 Dec 202631 Dec 2026On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology