Company or firm · first RERA registration 2023
Haware Properties Llp
Deedo IDDD-YK82None of 10 registrations has reached its promised completion date yet.
Projects510 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
9 registrations of 10 ran past the RERA date
Months late against the original RERA promise, per registration
10 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Haware My First Home Shil Phata Phase 1 Bldg 1P51700052794 | Thane | Certificate Signed | 31 Dec 2030 | 30 Apr 2031 | +4 mo |
| Haware My First Home Shil Phata Phase 1 Bldg 2P51700053825 | Thane (M Corp.) | Certificate Signed | 31 Dec 2030 | 30 Apr 2031 | +4 mo |
| Haware My First Home Shil PhataP51700053826 | Thane (M Corp.) | Certificate Signed | 31 Dec 2030 | 30 Apr 2031 | +4 mo |
| Haware My First Home Shil PhataP51700053915 | Thane (M Corp.) | Certificate Signed | 31 Dec 2030 | 31 Dec 2030 | On date |
| Haware Paramount KalyanP51700056061 | Muthaval | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
| Haware Palms KalyanP51700056190 | Muthaval | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
| Haware Paramount KalyanP51700076796 | Muthaval | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
| Haware Paramount KalyanP51700078127 | Muthaval | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
| Haware Paramount KalyanP51700080192 | Muthaval | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
| Haware Palms KalyanPR1330002501329 | Muthaval | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology