Hasthshilp Reality

Deedo IDDD-Y8D7

Of 3 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 22 mo late.

Projects13 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay22 mowhen late
Flats sold, all time17registered sale deeds
Regulatory cases0none on record

3 registrations of 3 ran past the RERA date

Months late against the original RERA promise, per registration

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Vertical AlciniaP52100007827MohammadwadiCertificate Signed30 Jun 201929 Dec 2020+18 mo
Vertical AlciniaP52100011957MohammadwadiActive31 Mar 2021—+67 mo*
Vertical AlciniaP52100012117MohammadwadiCertificate Signed30 Dec 202020 Oct 2022+22 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology