Of 4 registrations whose promised date has arrived, 2 kept it (50%). The rest ran a median 31 mo late.

Projects44 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay31 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 4 ran past the RERA date

Months late against the original RERA promise, per registration

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
SoordasP52100023121GultekadiCertificate Signed11 Jan 202311 Jan 2023+45 mo*
Ambar ViharP52100025090KothrudCertificate Signed28 Aug 202328 Aug 2023On date
AISHWARYAPURI C.H.S.Ltd.P52100026762Pune (M Corp.)Certificate Signed25 Mar 202325 Mar 2023On date
KalpanaP52100052449ParvatiCertificate Signed30 Jun 202530 Jun 2025+16 mo*
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology