Company or firm · first RERA registration 2019
Harivijay Infracon
Of 4 registrations whose promised date has arrived, 2 kept it (50%). The rest ran a median 31 mo late.
Projects44 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay31 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
2 registrations of 4 ran past the RERA date
Months late against the original RERA promise, per registration
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| SoordasP52100023121 | Gultekadi | Certificate Signed | 11 Jan 2023 | 11 Jan 2023 | +45 mo* |
| Ambar ViharP52100025090 | Kothrud | Certificate Signed | 28 Aug 2023 | 28 Aug 2023 | On date |
| AISHWARYAPURI C.H.S.Ltd.P52100026762 | Pune (M Corp.) | Certificate Signed | 25 Mar 2023 | 25 Mar 2023 | On date |
| KalpanaP52100052449 | Parvati | Certificate Signed | 30 Jun 2025 | 30 Jun 2025 | +16 mo* |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology