Individual promoter · first RERA registration 2018
Harish Sudhakar Shende
Of 1 registration whose promised date has arrived, 1 kept it (100%).
Projects22 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay0 monone ran late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
No registration has run past its RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Subhadra ResidencyP50400015669 | Palakwadi (Wardha) | Completed | 30 Sep 2020 | — | On date |
| Subhadra HeightP50400056263 | Sawangi (Meghe) (Ct) | Active | 31 Dec 2026 | — | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology
