Of 2 registrations whose promised date has arrived, 2 were never extended past it (100%).

Projects12 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delayNonewhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
Gulmohar Homes developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

No registration has been extended past its RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Gulmohar HomesP52100050183WagholiCertificate Signed31 Dec 202431 Dec 2024On date
Gulmohar HomesP52100050535WagholiCertificate Signed31 Dec 202431 Dec 2024On date