Gruhlaxmi Life Space Private Limited
Deedo IDDD-NPR3Of 4 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 25 mo late.
Delivery record
4 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Mahalaxmi City Phase IVP50500002498 | Bokhara | Certificate Signed | 20 Nov 2020 | 31 Dec 2022 | +25 mo |
| Mahalaxmi CityP50500002523 | Bokhara | Certificate Signed | 30 Nov 2020 | 29 May 2022 | +71 mo* |
| Mahalaxmi CityP50500002647 | Bokhara | Certificate Signed | 24 Nov 2020 | 24 May 2022 | +18 mo |
| Mahalaxmi City Phase VP50500017428 | Bokhara | Certificate Signed | 10 Nov 2020 | 31 Dec 2022 | +25 mo |
Gruhlaxmi Life Space Private Limited, in questions
Does Gruhlaxmi Life Space Private Limited finish projects on time?
Of 4 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 25 mo late. Across Maharashtra, 73% kept their date.
How many projects has Gruhlaxmi Life Space Private Limited registered with MahaRERA?
3 projects under 4 MahaRERA registrations; 3 completed on MahaRERA.
Does Gruhlaxmi Life Space Private Limited have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.