Grd Infraprojects Private Limited

Company or firm · 4 projects · 4 MahaRERA registrations

4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Gaurav PrideP52100007202Wakad2017Certificate Signed31 Dec 201731 Dec 2017On date
Westfield 3P52100026904Baner2020Certificate Signed31 Dec 202630 Apr 2027+4 months
Weone 121P52100049391Wakad2023Certificate Signed31 Dec 202630 Apr 2027+4 months
Weone 153P52100054963Wakad2024Certificate Signed31 Dec 202630 Apr 2027+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Gaurav PrideOn date
  • Westfield 3+4 mo
  • Weone 121+4 mo
  • Weone 153+4 mo

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 4 months, for Westfield 3 (P52100026904).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology