Company or firm · first RERA registration 2018
Gopinath Developers Llp
Deedo IDDD-BS24Of 3 registrations whose promised date has arrived, 3 kept it (100%).
Projects13 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay0 monone ran late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
No registration has run past its RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Ajmera ExoticaP52100015618 | Wagholi | Certificate Signed | 23 Feb 2023 | 23 Feb 2023 | On date |
| Ajmera ExoticaP52100023633 | Wagholi | Certificate Signed | 30 Dec 2024 | 30 Dec 2024 | On date |
| Ajmera ExoticaP52100023666 | Wagholi | Certificate Signed | 30 Dec 2024 | 30 Dec 2024 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology