Company or firm · first RERA registration 2017
Goldendream Buildcon Pvt Ltd
Deedo IDDD-NQNYOf 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 55 mo late.
Projects33 RERA registrations
Kept RERA date33%Maharashtra: 73%
Median delay55 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
2 registrations of 3 ran past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Millennium Park A1 To A4P51500002918 | Aurangabad | Certificate Signed | 30 Jun 2019 | 30 Jun 2019 | On date |
| Millennium Park A5 To A7P51500004485 | Aurangabad (M Corp.) | Certificate Signed | 30 Jun 2023 | 30 Jun 2023 | +40 mo* |
| Flamingo A1 To A4P51500005457 | Aurangabad (M Corp.) | Certificate Signed | 30 Dec 2020 | 29 Jun 2023 | +70 mo* |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology