Company or firm · first RERA registration 2021

Gokhale Schemes LLP

Deedo IDDD-VBZ9

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 10 mo late.

Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay10 mowhen late
Flats sold, all time1registered sale deeds
Regulatory cases0none on record

1 registration of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
GurusparshaP52100031507HaveliCertificate Signed31 Jul 202631 Jul 2026On date
Gokhale Business CornerP52100050102KothrudCertificate Signed31 Dec 202531 Dec 2025+10 mo*
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology