Company or firm · first RERA registration 2017
Ghodawat Infra Llp
Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 18 mo late — longer than Maharashtra's 4 mo.
Projects12 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay18 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
1 registration of 2 ran past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Life MontageP53000006727 | Sus | Certificate Signed | 30 Jun 2019 | 20 Dec 2020 | +18 mo |
| Life MontageP53000007829 | Sus | Certificate Signed | 31 Mar 2018 | 31 Mar 2018 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology
