Company or firm · first RERA registration 2017
Gayatri Enterprises
Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 94 mo late.
Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay94 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases1no insolvency
1 registration of 1 ran past the RERA date
Months late against the original RERA promise, per registration
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Suo motu order | Gayatri KrupaSuo motu order: Secretary, MahaRERA Versus Gayatri Enterprises.(Suo Motu Case No.188 of 2020) dated 16 March 2020 | 18 Mar 2022 |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Gayatri KrupaP52000011627 | Ulawe | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | +94 mo* |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology