Company or firm · first RERA registration 2017
Gangotree Greenbuild
Deedo IDDD-8ZFCOf 6 registrations whose promised date has arrived, 5 kept it (83%). The rest ran a median 24 mo late — longer than Maharashtra's 4 mo.
Projects66 RERA registrations
Kept RERA date83%Maharashtra: 73%
Median delay24 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
1 registration of 6 ran past the RERA date
Months late against the original RERA promise, per registration
6 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| PriyadarshanP52100003716 | Kothrud | Certificate Signed | 30 Apr 2018 | 30 Apr 2018 | On date |
| SuhrudP52100013402 | Pune (M Corp.) | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| Pooja NiwasP52100014775 | Katraj | Certificate Signed | 30 Dec 2022 | 31 Dec 2024 | +24 mo |
| Saleel16P52100029108 | Parvati | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | On date |
| Saleel21P52100029109 | Parvati | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | On date |
| LaxmikrupaP52100045252 | Kothrud | Certificate Signed | 30 Jun 2026 | 30 Jun 2026 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology