Company or firm · first RERA registration 2017
Gandhi Bafna Construction Private Limited
Deedo IDDD-XEX3Of 3 registrations whose promised date has arrived, 2 kept it (67%). The rest ran a median 56 mo late.
Projects33 RERA registrations
Kept RERA date67%Maharashtra: 73%
Median delay56 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
1 registration of 3 ran past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Swapnalok- Building CP52100005515 | Haveli | Certificate Signed | 31 Mar 2018 | 31 Mar 2018 | On date |
| Swapnalok- Building BP52100006177 | Bopodi | Certificate Signed | 28 Feb 2022 | 31 Mar 2023 | +56 mo* |
| Aayan- Building 2P52100007092 | Wagholi | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology