Gagan Unnati Ventures

Of 2 registrations whose promised date has arrived, 0 were never extended past it (0%).

Projects22 RERA registrations
Kept RERA date0%
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record
Gagan Unnati Ventures developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

2 registrations of 2 moved past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
Gagan Unnatii Phase 2P52100001818KatrajCertificate Signed31 Mar 201930 Sep 2020+18 mo
Gagan Unnatii Phase 3P52100016561Kondhwa BkCertificate Signed31 Dec 202031 Dec 2024+48 mo