Company or firm · first RERA registration 2018
Gagan ILand Township Private Limited
Deedo IDDD-XM56Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 31 mo late.
Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay31 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases2includes insolvency
1 registration of 1 ran past the RERA date
Months late against the original RERA promise, per registration
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Deregistered | Gagan Commerce CentreDeregistered: Gagan Commerce Centre | Not on record |
| Listed as an NCLT insolvency project | Gagan Commerce CentreListed as NCLT project: Gagan Commerce Centre | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Gagan Commerce CentreP52100016445 | Pune (M Corp.) | Certificate Signed | 30 Mar 2024 | 30 Mar 2024 | +31 mo* |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology