Gadkari Builders & Associates

Deedo IDDD-THE2

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 7 mo late.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay7 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases1no insolvency

Delivery record

2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Srushti EnclaveP51900011095KurlaCertificate Signed30 Dec 202530 Dec 2025+10 mo*
Gadkari ParadiseP51900011571Mumbai CityCertificate Signed31 Dec 203030 Apr 2031+4 mo

Gadkari Builders & Associates, in questions

Does Gadkari Builders & Associates finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 7 mo late. Across Maharashtra, 73% kept their date.

How many projects has Gadkari Builders & Associates registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.

Does Gadkari Builders & Associates have MahaRERA regulatory cases?

1 regulatory case name its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology