Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 6 mo late — longer than Maharashtra's 4 mo.

Projects12 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay6 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Shubh AanganP51800005320KurlaCertificate Signed31 Dec 202130 Jun 2022+6 mo
Shubh AanganP51800029568KurlaCertificate Signed31 Dec 202331 Dec 2023On date