Five Star Construction Company

Deedo IDDD-SEA1

Of 9 registrations whose promised date has arrived, 7 kept it (78%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.

Projects99 RERA registrations
Kept RERA date78%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 9 ran past the RERA date

Months late against the original RERA promise, per registration

9 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Royal Entrada Phase IIP52100000526MulshiCertificate Signed31 Dec 201931 Dec 2019On date
Royal MajesticP52100000548Pimpri Chinchawad (M Corp.)Certificate Signed31 Mar 201831 Mar 2018On date
Royal ImpressionsP52100014526BopodiCertificate Signed30 Dec 202030 Dec 2020On date
Royal GrandeP52100015350WakadCertificate Signed30 Dec 202230 Dec 2022On date
Royal MysticP52100016160Pimpri Chinchawad (M Corp.)Certificate Signed30 Oct 202130 Oct 2021On date
Anp - LandmarkP52100023061WakadCertificate Signed30 Mar 202330 Mar 2023On date
Anp MementoP52100026219MulshiCertificate Signed30 Sep 202630 Jan 2027+4 mo
Anp RetreatP52100034557WakadCertificate Signed31 Aug 202631 Dec 2026+4 mo
Royal AceP52100077036WakadCertificate Signed31 Mar 202631 Mar 2026On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology