Company or firm · first RERA registration 2017

Fiona Realty Private Limited

Deedo IDDD-KVSR

Of 4 registrations whose promised date has arrived, 1 kept it (25%). The rest ran a median 10 mo late.

Projects24 RERA registrations
Kept RERA date25%Maharashtra: 73%
Median delay10 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

3 registrations of 4 ran past the RERA date

Months late against the original RERA promise, per registration

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Vision HeightsP51800003396AndheriCertificate Signed30 Dec 202530 Dec 2025+10 mo*
Vision HeightsP51800007259AndheriCertificate Signed29 Dec 20244 Jun 2025+6 mo
Vision Heights Wing AP51800008700AndheriCertificate Signed30 Dec 202530 Dec 2025+10 mo*
Vision HeightsP51800010431AndheriCertificate Signed30 Dec 202330 Dec 2023On date
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology