Deedo IDDD-KVSROf 4 registrations whose promised date has arrived, 1 kept it (25%). The rest ran a median 10 mo late.
Projects24 RERA registrations
Kept RERA date25%Maharashtra: 73%
Median delay10 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
3 registrations of 4 ran past the RERA date
Months late against the original RERA promise, per registration
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Vision HeightsP51800003396 | Andheri | Certificate Signed | 30 Dec 2025 | 30 Dec 2025 | +10 mo* |
| Vision HeightsP51800007259 | Andheri | Certificate Signed | 29 Dec 2024 | 4 Jun 2025 | +6 mo |
| Vision Heights Wing AP51800008700 | Andheri | Certificate Signed | 30 Dec 2025 | 30 Dec 2025 | +10 mo* |
| Vision HeightsP51800010431 | Andheri | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |