Company or firm · first RERA registration 2017
Fast Realty Pvt Ltd
Of 2 registrations whose promised date has arrived, 1 were never extended past it (50%). When extended, the date moved a median 5 mo — longer than Maharashtra's 4 mo.
Projects13 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay5 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
2 registrations of 3 moved past the RERA date
Months late against the original RERA promise, per registration
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Somani Dream HomeP52100002272 | Punawale | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| Somani Dream HomeP52100014395 | Punawale | Certificate Signed | 30 Dec 2022 | 30 Jun 2023 | +6 mo |
| Somani Dream HomePR1260002600395 | Punawale | Certificate Signed | 31 Dec 2031 | 30 Apr 2032 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology