Eversmile Properties Private Limited

None of 9 registrations has reached its promised completion date yet.

Projects99 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

5 registrations of 9 ran past the RERA date

Months late against the original RERA promise, per registration

9 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Sector 2A - Wing BP51700028685Mirabhayandar (M Corp.)Certificate Signed30 Dec 202730 Dec 2027On date
Sector 2A - Wing HP51700028686Mirabhayandar (M Corp.)Certificate Signed30 Dec 202730 Dec 2027On date
Sector 2A - Wing GP51700029365Mirabhayandar (M Corp.)Certificate Signed30 Jun 202729 Jun 2028+12 mo
Sector 2A - Wing AP51700029367Mirabhayandar (M Corp.)Certificate Signed30 Jun 202730 Jun 2027On date
Sector 2A - Wing CP51700033851Mirabhayandar (M Corp.)Certificate Signed30 Jun 202730 Jun 2027On date
Sector 2A - Wing DP51700047329Mirabhayandar (M Corp.)Certificate Signed30 Jun 202830 Oct 2028+4 mo
Sector 2A - Wing EP51700053089Mirabhayandar (M Corp.)Certificate Signed30 Jun 202830 Oct 2028+4 mo
Sector 2A - Wing FP51700053195Mirabhayandar (M Corp.)Certificate Signed30 Jun 202830 Oct 2028+4 mo
Sector 2A - Wings JKLPR1338082400025ThaneCertificate Signed31 Dec 202930 Apr 2030+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology