Ethics Infra Development Pvt. Ltd
Of 4 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 11 mo late — longer than Maharashtra's 4 mo.
Projects44 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay11 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
4 registrations of 4 ran past the RERA date
Months late against the original RERA promise, per registration
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Krishna Chaitanya Rajbhavan ChslP51800000078 | Andheri | Certificate Signed | 31 Dec 2018 | 30 Oct 2020 | +22 mo |
| Chaitanya ResidencyP51800000886 | Borivali | Certificate Signed | 30 Apr 2018 | 31 Oct 2018 | +6 mo |
| Ashwini Residency Borivali Ashwini ChslP51800000982 | Borivali | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 mo |
| The Greens - RadhakunjP51800029355 | Borivali | Certificate Signed | 31 May 2024 | 14 Feb 2025 | +9 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology