Company or firm · first RERA registration 2017
Empress Developers
Deedo IDDD-4PDROf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 54 mo late — longer than Maharashtra's 4 mo.
Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay54 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases1no insolvency
1 registration of 1 ran past the RERA date
Months late against the original RERA promise, per registration
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Regulatory order | Eiffel TowerRegulatory order: PROJECT NAME: EIFFEL TOWER (Regulatory Case No. 280 OF 2024) dated 09 Aug 2024. | 9 Aug 2024 |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Eiffel TowerP51900007758 | Mumbai City | Certificate Signed | 30 Jun 2023 | 31 Dec 2027 | +54 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology