Company or firm · first RERA registration 2017
Elevated Avenue Realty LLP
Deedo IDDD-2GCDNone of 7 registrations has reached its promised completion date yet.
Projects47 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
5 registrations of 7 ran past the RERA date
Months late against the original RERA promise, per registration
7 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Centrona ZestP51800003201 | Kurla | Certificate Signed | 30 Dec 2026 | 30 Apr 2027 | +4 mo |
| Centrona ZestP51800003446 | Kurla | Certificate Signed | 30 Dec 2026 | 30 Apr 2027 | +4 mo |
| Centrona NovaP51800004566 | Kurla | Certificate Signed | 30 Jun 2027 | 30 Jun 2027 | On date |
| Centrona NovaP51800005456 | Kurla | Certificate Signed | 30 Jun 2027 | 30 Jun 2027 | On date |
| Centrona ZenP51800006139 | Kurla | Certificate Signed | 30 Dec 2026 | 30 Apr 2027 | +4 mo |
| Centrona ZenP51800006239 | Kurla | Certificate Signed | 30 Dec 2026 | 30 Apr 2027 | +4 mo |
| L&T Realty HarmonyPM1180002600841 | Bandra | Certificate Signed | 31 Aug 2028 | 31 Dec 2028 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology