Company or firm · first RERA registration 2024

Elante Properties Private Limited

None of 4 registrations has reached its promised completion date yet.

Projects44 RERA registrations
Kept RERA dateNone due yet
Median delayNonewhen extended
Completed0as reported on MahaRERA
Regulatory cases0none on record
Elante Properties Private Limited developer report cardPDF: every registration against its promise, regulatory matters, professionals and projects by salesSee what's inside · from ₹1,999

4 registrations of 4 moved past the RERA date

Months late against the original RERA promise, per registration

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityStatusProposedRevisedDelay
L and T Realty Evara Heights T1P51700077650Thane (M Corp.)Certificate Signed31 Aug 203031 Dec 2030+4 mo
L and T Realty Evara Heights T2P51700077678Thane (M Corp.)Certificate Signed31 Aug 203031 Dec 2030+4 mo
L and T Realty Evara Heights T4P51700077681Thane (M Corp.)Certificate Signed30 Apr 203030 Aug 2030+4 mo
L and T Realty Evara Heights T5P51700078362Thane (M Corp.)Certificate Signed30 Apr 203030 Aug 2030+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology