Company or firm · first RERA registration 2018

Ekta Developers

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.

Projects34 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

3 registrations of 4 ran past the RERA date

Months late against the original RERA promise, per registration

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
EktaP52800015043Chiplun (M Cl)Certificate Signed25 Dec 202324 Dec 2024+12 mo
EktaP52800016459Chiplun (M Cl)Certificate Signed25 Dec 202325 Dec 2023On date
Ekta UniqueP52800020760Chiplun (M Cl)Certificate Signed31 Dec 202630 Apr 2027+4 mo
Ekta HeightsP52800079383DhamanvaneCertificate Signed31 Dec 202730 Apr 2028+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology