Eastend Spaces Llp

Deedo IDDD-BQR2

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 25 mo late.

Projects14 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay25 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

3 registrations of 4 ran past the RERA date

Months late against the original RERA promise, per registration

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
MeanderP52100027109WagholiCertificate Signed30 Sep 202430 Sep 2024+25 mo*
MeanderP52100033367WagholiCertificate Signed31 Mar 202431 Mar 2024+31 mo*
MeanderP52100051553WagholiCertificate Signed31 Dec 202631 Dec 2026On date
MeanderP52100080928WagholiCertificate Signed31 Dec 202830 Apr 2029+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology