Earth Home
Deedo IDDD-YZ0ZOf 2 registrations whose promised date has arrived, 2 kept it (100%).
Delivery record
None of 2 registrations with dates has moved or missed its RERA date
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Shree Sadguru ComplexP52000007811 | Khalapur | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
| Shree Sadguru ComplexP52000011306 | Khalapur | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
Earth Home, in questions
Does Earth Home finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 2 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Earth Home registered with MahaRERA?
1 project under 2 MahaRERA registrations; 2 completed on MahaRERA.
Does Earth Home have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.