Dweepmala Developers
Of 2 registrations whose promised date has arrived, 2 were never extended past it (100%).
Projects22 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delayNonewhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
No registration has been extended past its RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Baline RoyaleP52000001492 | Taloje Panchnad | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
| Baline DwellingsP52000014722 | Ulawe | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology