Company or firm · first RERA registration 2017

Dmk Infrastructure Pvt Ltd

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.

Projects99 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

7 registrations of 9 ran past the RERA date

Months late against the original RERA promise, per registration

9 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
StellaP52100002747BhosariCertificate Signed24 Feb 201924 Feb 2019On date
Crown C1P52100020978HaveliCertificate Signed11 Oct 202210 Oct 2023+12 mo
Stella B1P52100053511MulshiCertificate Signed1 Nov 20261 Mar 2027+4 mo
Stella F1P52100054567MulshiCertificate Signed9 Jan 20279 May 2027+4 mo
Stella D3P52100054604MulshiCertificate Signed9 May 20279 Sep 2027+4 mo
Stella F3P52100054729MulshiCertificate Signed31 Mar 202731 Mar 2027On date
Stella B2PR1260002500956MoshiCertificate Signed27 Mar 202827 Jul 2028+4 mo
Stella B3PR1260002600852DudulgaonCertificate Signed31 Mar 202931 Jul 2029+4 mo
Stella APR1260002600937DudulgaonCertificate Signed31 Dec 202930 Apr 2030+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology