Dmk Infrastructure Pvt Ltd
Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.
Projects99 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
7 registrations of 9 ran past the RERA date
Months late against the original RERA promise, per registration
9 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| StellaP52100002747 | Bhosari | Certificate Signed | 24 Feb 2019 | 24 Feb 2019 | On date |
| Crown C1P52100020978 | Haveli | Certificate Signed | 11 Oct 2022 | 10 Oct 2023 | +12 mo |
| Stella B1P52100053511 | Mulshi | Certificate Signed | 1 Nov 2026 | 1 Mar 2027 | +4 mo |
| Stella F1P52100054567 | Mulshi | Certificate Signed | 9 Jan 2027 | 9 May 2027 | +4 mo |
| Stella D3P52100054604 | Mulshi | Certificate Signed | 9 May 2027 | 9 Sep 2027 | +4 mo |
| Stella F3P52100054729 | Mulshi | Certificate Signed | 31 Mar 2027 | 31 Mar 2027 | On date |
| Stella B2PR1260002500956 | Moshi | Certificate Signed | 27 Mar 2028 | 27 Jul 2028 | +4 mo |
| Stella B3PR1260002600852 | Dudulgaon | Certificate Signed | 31 Mar 2029 | 31 Jul 2029 | +4 mo |
| Stella APR1260002600937 | Dudulgaon | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology